16 January 2024 |
- Follow up actions from the 2023 ion run (R. Bruce)
- News on 10 Hz events (J. Wenninger)
- Analysis of the performance during the ion run (N. Triantafyllou)
|
13 February 2024 |
- tatus of the ML tool for longitudinal injection data (K. Iliakis)
- Beam commissioning 2024
|
27 February 2024 |
- Partial RP optics for 2024 (S. Fartoukh)
- Collimation settings and commissioning in 2024 (F. Van Der Veken)
|
5 March 2024 |
- News on 13L8 (J. Wenninger)
- Scrubbing plans and 2024 filling scheme options (L. Mether)
- Bunch Length observations in 2023 Operation (J. Wenninger)
- Beam induced heating of warm vacuum modules for operational beams and MDs (C. Zannini)
|
19 March 2024 |
- Results of 13L8 vibration tests (M. Guinchard)
- Octupole settings in 2024 for different configurations (X. Buffat)
- Discussion 93cm - 120 cm
|
26 March 2024 |
- Bunch length control in the cycle (H. Timko)
- Proposal for the 2024 wires-compensation knobs (G. Sterbini)
|